arise
Mireia was the Process Coordinator responsible for full process installation and optimisation, of 2 turnkey solar cell production lines (mono & multicrystalline) at a customer in Germany. Step by step, working close to the process technologists and the customer, and making use of DfSS (Design for 6-sigma) methodology, each process step in the production line was optimised, until required yield and cell efficiency were achieved.
After all milestones were successfully achieved, the line was transferred to customer for production; followed by final payment of some million €. Thanks to DfSS methodology and to the close collaboration with customer, short ramp-up times were possible. Mireia received a special acknowledgement for her work, from OTB Solar management.

Con: OTB Solar (currently Roth & Rau) and TMC.